| Date▲▼ | Event Type▲▼ | Disposition▲▼ | Remarks | Document |
| 12/14/2011 | Motion for Extension of Time to File Petition for Review disposed | Filing granted |
Petition is due January 2, 2012.
|
|
| 12/07/2011 | Motion for Extension of Time to File Petition for Review #2 filed | |
E-FILED Respondent Martin K. Eby Construction Company, Inc.'s Unopposed Motion for Extension of Time to file Conditional Cross-Petition for Review
|
|
| 12/07/2011 | Response Waiver filed | |
E-FILED Response waiver filed on behalf of Martin E. Eby Constr. Co.
|
|
| 11/29/2012 | Case Record Filed | |
|
|
| 11/28/2012 | Phone call from Clerk's Office | |
To Lerone Landis, deputy clerk at the 5th COA to inquire about the status of exhibit requested from their court on 11/13/12.
|
|
| 11/26/2013 | Post submission brief filed | |
Post-Submission Letter Brief filed on behalf of Martin K. Eby Construction Co., Inc. (Hard Copies Received)
|
|
| 11/13/2012 | Record Requested in Case | |
EXHIBIT 2059 (aka EXHIBIT M) requested from the 5th COA
|
|
| 11/10/2011 | Appendix Filed | |
E-FILED Petition, appendix attached, filed on behalf of LAN/STV, a Joint Venture of Lockwood.
|
|
| 11/10/2011 | Petition for Review | |
E-FILED Petition appendix attached, filed on behalf of LAN/STV, a joint venture of Lockwood. (HARD COPIES REC'D)
|
|
| 11/09/2012 | Reply Brief | |
Reply Brief on the Merits filed on behalf of LAN/STV. (HARD COPIES REC'D)
|
|
| 11/05/2012 | Motion for Extension of Time disposed. | Filing granted |
LAN/STV's Motion for a 10day Extension to file Reply Brief is granted. LAN's Reply Brief is due November 12, 2012. NO FURTHER EXTENSIONS OF TIME FOR THIS FILING WILL BE CONSIDERED.
|
|
| 11/02/2012 | Reply Brief | |
Reply Brief on the Merits filed on behalf of Martin E. Eby Constr. Co. HARD COPIES RECEIVED.
|
|
| 10/30/2012 | Motion for Extension of Time to File Brief filed | |
Unopposed Motion for a Ten-Day Extension of Time to file its Reply in support of its Brief on the Merits. On behalf of Petitioner/Cross-Respondent, LAN/STV.
|
|
| 10/26/2011 | Second Motion for Extension of Time to File Petition for Review disposed | Filing granted |
Petition for review is due November 10, 2011. FURTHER REQUESTS FOR EXTENSIONS OF TIME FOR THIS FILING WILL BE DISFAVORED.
|
|
| 10/24/2011 | Second Motion for Extension of Time to File Petition for Review filed | |
E-FILED Unopposed motion for extension of time to file petition for review filed on behalf of LAN/STV.
|
|
| 10/19/2012 | Motion for Extension of Time disposed. | Filing granted |
JOINT Motio for 2weeks Extension of Time is granted. Petitioners' Reply Briefs are due on November 2, 2012. FURTHER REQUESTS FOR EXTENSIONS OF TIME FOR THIS FILING WILL BE DISFAVORED.
|
|
| 10/16/2012 | Motion for Extension of Time to File Brief filed | |
Cross-Petitioner Martin K. Eby Construction Co. & Petitioner LAN/STV's JOINT Motion for Two Week Extension of Time to file Reply Briefs.
|
|
| 10/13/2011 | Motion for Extension of Time to File Petition for Review disposed | Filing granted |
Petition is due October 27, 2011.
|
|
| 10/11/2013 | Post submission brief filed | |
Post-Submission Letter Brief filed on behalf of LAN/STV.
|
|
| 10/10/2011 | Motion for Extension of Time to File Petition for Review filed | |
E-FILED Unopposed Motion for Two-Week Extension of Time to File Petition for Review. On behalf of LAN/STV.
|
|
| 10/08/2013 | Oral argument | |
argued on behalf of petitioners by Thomas C. Wright; argued on behalf of respondents by Jeffrey S. Levinger
|
|
| 10/08/2013 | Oral argument | |
argued on behalf of petitioners by Thomas C. Wright; argued on behalf of respondents by Jeffrey S. Levinger
|
|
| 10/04/2012 | Brief on the Merits | |
Response Brief on the Merits filed on behalf of LAN/STV. (HARD COPIES REC'D)
|
|
| 10/04/2012 | Brief on the Merits | |
Respondent Martin K. Eby Construction Co., Inc.'s Response to Brief on the Merits. (HARD COPIES REC'D)
|
|
| 09/10/2012 | Motion for Extension of Time disposed. | Filing granted |
Response brief due 10/04/12; Reply brief due 10/19/12; FURTHER REQUESTS FOR EXTENSION OF TIME FOR THIS FILING WILL BE DISFAVORED.
|
|
| 08/28/2013 | Oral Argument Submission Form from Attorney received | |
Oral argument submission form submitted by petitioner/cross-respondent attorney Thomas C. Wright of Wright & Close, LLP of Houston, TX
|
|
| 08/28/2013 | Oral Argument Submission Form from Attorney received | |
Oral argument submission form submitted by respondent/cross-petitioner attorney Jeffrey S. Levinger of Levinger PC of Dallas, TX
|
|
| 08/28/2012 | Motion for Extension of Time to File Brief filed | |
Unopposed Joint Motion for Extension of Time to File Response Briefs on the Merits filed on behalf of LAN/STV, et al.
|
|
| 08/22/2012 | Fully hyperlinked brief filed | |
Hyperlinked Petitioner's Brief on the Merits filed on behalf of LAN/STV.
|
|
| 08/15/2012 | Brief on the Merits | |
Petitioner's Brief on the Merits filed on behalf of LAN/STV. (HARD COPIES REC'D)
|
|
| 08/15/2012 | Brief on the Merits | |
Brief on the Merits in Support of Conditional Cross-Petition for Review filed on behalf of Martin K. Eby Construction Co., Inc. (HARD COPIES REC'D)
|
|
| 08/07/2014 | Case Stored | |
G02 Row 14 A-3 (2 vols)
|
|
| 08/01/2014 | Mandate issued | |
Mandate & Cost Bill Issued
|
|
| 07/25/2012 | Case Record Filed | |
Electronic Appellate Record received from the 5th Court of Appeals.
|
|
| 07/11/2012 | Motion for Extension of Time disposed. | Filing granted |
Motion for Extension of Time is granted. Petitioner's Brief is due August 15; Respondent's Brief is due September 4, 2012; Reply Brief is due September 19, 2012.
|
|
| 07/10/2012 | Motion for Extension of Time to File Brief filed | |
Joint Motion for Extension of Time to file Petition for Review filed on behalf of LAN/STV and Martin K. Eby Constr. Co.
|
|
| 07/09/2013 | Address Change | |
Notice of Change of Address for Petitioner's Counsels. Effective July 1, 2013. On behalf of LAN/STV.
|
|
| 06/20/2014 | Court approved judgment sent to attorneys of record | Issued |
|
|
| 06/20/2014 | Opinion issued | Issued |
|
|
| 06/20/2014 | Opinion issued | Court of Appeals' judgment reversed & judgment rendered |
The Court reverses the court of appeals' judgment and renders judgment. Chief Justice Hecht delivered the opinion of the Court.
|
|
| 06/19/2012 | Record Requested in Case | |
|
|
| 06/15/2012 | Brief on the Merits Ordered | |
Brief on the merits requested: Petitioner's brief due no later than 7/16/12; Response brief due 8/6/12; Reply brief due 8/21/12.
|
|
| 05/25/2012 | Reply to Response | |
Reply in Support of Petition for Review filed on behalf of LAN/STV, et al. (HARD COPIES REC'D)
|
|
| 05/18/2012 | MET to file reply disposed of | Filing granted |
LAN/STV's Unopposed Motion for an Eight-Day Extension of Time to File its Reply granted. Reply is due May 25, 2012. FURTHER REQUESTS FOR EXTENSIONS OF TIME FOR THIS FILING WILL BE DISFAVORED
|
|
| 05/09/2012 | Motion to Extend Time to File Reply filed | |
Petitioner, LAN/STV's Unopposed Motion for an Eight-Day Extension of Time to File its Reply in Support of its Petition for Review
|
|
| 05/03/2013 | Case set for oral argument | Case set for oral argument |
This cause has been set for oral argument at 9:00 a.m., October 8, 2013. Time allotted to argue: 20/20 minutes.
|
|
| 05/03/2013 | Case set for oral argument | Case set for oral argument |
This cause has been set for oral argument at 9:00 a.m., October 8, 2013. Time allotted to argue: 20/20 minutes.
|
|
| 05/02/2012 | Response to Petition | |
Response to Petition for Review filed on behalf of Martin K. Eby Construction Company, Inc. (HARD COPIES REC'D)
|
|
| 04/02/2012 | Response to Petition | |
E-FILED Petitioner/cross-Respondent Lan/Stv's Response to Eby's Cross-Petition. (HARD COPIES REC'D)
|
|
| 03/21/2012 | Motion for Extension of Time to File Response disposed | Filing granted |
Motion to Extend Time to file is granted. Response is due May 2, 2012. FURTHER REQUESTS FOR EXTENSIONS OF TIME FOR THIS FILING WILL BE DISFAVORED.
|
|
| 03/21/2012 | Motion for Extension of Time to File Response | |
Unopposed Motion for Extension of Time to file Response filed on behalf of Martin K. Eby Construction Co.
|
|
| 03/18/2014 | Amicus Curiae Brief received | |
Amicus Curiae Brief filed on behalf of General Contractors of Texas, Inc.
|
|
| 03/04/2014 | Amicus Curiae Brief received | |
Amiucs letter brief filed on behalf of Atkins North America, Inc.
|
|
| 03/01/2013 | Electronic communication received from Party | |
Attorney Jeff Levinger sent an email to the Clerk requesting that this case not be scheduled the same week as 11-0709, Kia v. Ruiz, in which he is also representing one of the parties. The Clerk replied that the staff would try to accomodate this request.
|
|
| 03/01/2012 | Supreme Court of Texas Requested Response | |
Requested responses to petitions for review due no later than 4/2/12.
|
|
| 02/15/2013 | Petition for Review disposed | Filing granted |
Date and time of oral argument are yet to be determined.
|
|
| 02/15/2013 | Petition for Review granted | |
|
|
| 02/15/2013 | Petition for Review disposed | Filing granted |
Date and time of oral argument are yet to be determined.
|
|
| 02/15/2013 | Petition for Review granted | |
|
|
| 02/11/2014 | Post submission brief filed | |
Post-Submission Brief filed on behalf of CCE, Inc.
|
|
| 02/07/2012 | Case forwarded to Court | |
|
|
| 02/07/2012 | Case forwarded to Court | |
|
|
| 01/02/2012 | Appendix Filed | |
Attached to Petition
|
|
| 01/02/2012 | Petition for Review #2 | |
E-FILED Petition appendix attached filed on behalf of Martin E. Eby Constr. Co. (HC REC'D)
|
|